eastmalling.net

Gas works in Chapman Way

Friday 20th July 2018

SGN reports as follows:

Phase one – approximately two weeks

From Monday 23 July, we will be working in Chapman Way between its
junctions with Catlyn Close and New Road. We’ll need to install
temporary traffic lights around our work area to ensure everyone’s
safety.

We’ll also need to temporarily close Beech Road between its junction
with Lime Crescent and The Malling School. Access will be maintained for
residents.

Phase two – approximately seven weeks

On Monday 23 July we’ll be working in New Road between with 2 New Road
and its junction with Chapman Way. To keep the traffic flowing we’ll
need to install temporary traffic lights around our work area.



Phase three – approximately two weeks

From Monday 30 July we’ll be working in Beech Road between its junctions
with Elm Crescent and New Road. Temporary traffic lights will be
installed around our work area to keep everyone safe.

We’ll also be working in Catlyn Close and around its junction with Chapman Way.

Make a comment